
|
OUTER HOUSE, COURT OF SESSION [2009] CSOH 4 |
|
|
P1531/08 |
OPINION OF LADY CLARK OF CALTON in the Petition of G Petitioners; For Judicial Review ญญญญญญญญญญญญญญญญญ________________ |
Petitioner:
First Respondents:
Second Respondents: Martin QC; Tods Murray LLP
13 January 2009
Summary
[1] In this case the petitioners
are heritable proprietors of an area of land at Tullochgribban (also known as
Tullochgorum). The petitioners seek
declaratory and reduction remedies, in terms of paragraph 11 of the petition,
in relation to the approval by the first respondents of purported new planning
conditions applicable to a dormant mineral site at Tullochgribban. The first respondents are the Highland
Council who are the planning authority for the purpose of approving said
conditions in terms of the Town and Country Planning (
Submissions on behalf of the petitioners
[2] Senior counsel for the
petitioners set out the heritable rights of the petitioners and second
respondents under reference to paragraph 2 of the petition and 6/1 - 8 of
process. Under reference to paragraph 3
of the petition, he explained that the second respondents' predecessor in title
obtained planning permission in 1965 (the "1965 permission"). That permission is set out in 6/3 of
process. The 1965 permission permitted, "the
working of minerals on land at Tullochgorum, Carrbridge, in accordance with the
plan (s) submitted to the council and docketed as relative hereto" subject to
certain specified conditions. Senior
counsel submitted that one of the difficulties in the case is that no plan or
any copies thereof are now known to exist.
Despite a difference in the names Tullochgribban and Tullochgorum, it
was not disputed that both names referred to the same location which is shown
on the map in the schedule attached to the petition. The said map indicates three boundary areas to
which reference was made in this dispute between the parties. The larger red boundary area, in broad terms,
represents the area in respect of which the mineral rights are held by the
second respondents and the area of land owned by the petitioners. A green boundary area and a yellow boundary area
are also delineated on said map. The
former corresponds with the green boundary area on the plan
[3] Senior
counsel for the petitioners set out the legislative framework. Certain legislative provisions were
introduced in the Environment Act 1995 ("the 1995 Act") section 6 and Schedule
13 in respect of permissions such as 6/3 of process for the winning and working
of minerals granted by any planning authority between 1948 and 1982. There was a re-enactment of said statutory
provisions in essentially the same terms in respect of Scotland by the Town and
Country Planning (Scotland) Act 1997 ("the 1997 Act") Schedule 9. The aforesaid provisions of the 1997 Act had
a commencement date of
[4] It
was submitted by senior counsel for the petitioners that the next relevant
event occurred in or about 2006 when land agents for the second respondents
became involved in discussions with the first respondents to agree new
conditions to which the relevant planning permission would be subject to enable
activation of the dormant Tullochgribban site.
Thereafter there was correspondence between said land agents and the
first respondents (6/7/1-4 of process and 6/8) whereby the first respondents agreed
to proceed on a boundary corresponding to the red boundary area with some
adjustment. The details are set out in
said correspondence. Thereafter on
[5] The criticism made by senior counsel for the petitioners was that the first respondents have commenced or purported to deal with the application by the second respondents on the basis that the mineral site listed was the site defined by the adjusted red boundary area, not the more limited green boundary area which was the area shown on the site plan referred to in the listing decision 6/6/1 to 6/6/3 of process. He submitted this was the critical issue in the case.
[6] The
legal submission of senior counsel for the petitioners may be summarised as
follows: in purporting to determine an application for approval of conditions
in respect of the 1965 planning permission, the first respondents had acted ultra vires in determining that it is
entitled to do so on the basis of the adjusted red boundary area, an area of ground
larger than that referred to in 6/6/1-3 of process. Senior counsel submitted that it is not
disputed that the plan which defines the area of land to which the 1965
planning permission extends is missing and was missing at the time of the
listing in 1997. He submitted under
reference to Schedule 9 paragraph (12) that when the then planning
authority issued the first list (6/4 of process), the Tullochgribban site was
not included in the list of mineral sites.
He submitted under reference to Schedule 9 paragraph (12) that the legal
effect of that, had no action been taken on behalf of the second respondents,
would have been that the planning permission which existed in respect of the
Tullochgribban site would have been extinguished. He submitted that it is plain from the
legislation that a pre existing right of planning permission may be
extinguished in full if listing is not achieved timeously. In this case full extinction of planning
permission did not result because application was made for inclusion of
Tullochgribban on the first list as a Phase 1 active site (6/5/1-3 of process). The application referred to a plan showing the
red boundary area. It was submitted that
the planning authority were entitled to accede to said application in respect of
all, or part only, of the land identified in the application. The planning authority were also entitled to decide
that it was a dormant site not an active site.
The planning authority was entitled to list the site which it considered
to be correct, in the sense that there had been issued a relevant planning
permission in respect of the site. The
planning authority was not limited to listing what was submitted to it by an
applicant for inclusion on the list.
Senior counsel submitted that on a proper interpretation of the
correspondence of 15 July and the enclosures (6/6/1-3 of process) it is plain
that the planning authority, by the administrative act in response to the
application, made its decision. That
decision inter alia listed a site identified
and specified by the green boundary area not the red boundary area for which
application had been made. The only
inference is that the site listed as a dormant site is the site referred to in
the plan attached to the decision in the letter of
[7] Senior
counsel submitted that in response to the listing decision of
[8] Senior
counsel for the petitioner referred to R v
North Lincolnshire Council, ex parte Horticultural and Garden Products Sales
(Humberside) Limited 1998 ENV.L.R. 295.
He relied on this case to demonstrate that the equivalent legislation applicable
in
Submissions on behalf of the first respondents
[9] Senior counsel referred to the
first respondents' answers. He also
sought to rely on the affidavit of Andrew Brown (7/4 of process) in order to
demonstrate the reasons that the first respondents were satisfied that the red
area was the area for which planning permission subsists.
[10] The correspondence relied on by the petitioners was not in dispute. It was admitted that the plan attached to the 1965 permission could not be found in 1997 or subsequently. It was not in dispute that the respondents are minded to treat the red area as adjusted as the area for which planning permission subsists for the purposes of the application for conditions. There was dispute about the legal effect of the correspondence and listing in 1997.
[11] It was submitted on behalf of the first respondents that the legal effect of the listing of Tullochgribban, Carrbridge, Baddingdock and Strathspey (7/1 of process) was to preserve the pre-existing 1965 planning permission in respect of said site in terms of Schedule 9 paragraph 12 (4). Senior counsel accepted that guidance had been issued which referred to further specification and a plan (7/2 of process par 28). The guidance was not made part of the rules of the statutory scheme which were relevant in the present case. He contrasted the specific reference in Schedule 9 paragraph 1 (3) to the requirement to "have regard to any guidance" with the absence of such specific reference in relation to other parts of Schedule 9. He submitted that the statutory scheme of listing merely required a listing of the site without any definition of boundaries in the listing. The planning authority, in order to satisfy the terms of the legislation and preserve the planning permission, merely had to list the site. The statutory listing process was a preliminary exercise, intended to be done quickly and without extensive investigation. The legislation was not intended to be interpreted in such a way as to deprive property owners of valuable rights. Senior counsel referred to Craie's statute law, paragraph 19.8, a passage dealing with the presumption against expropriation. He pointed out that there were no compensation provisions in relation to the extinction in whole or in part of planning permission. He emphasised, under reference to paragraph 3 (1) and the definition of mineral site in paragraph 1 (2), that what was being listed for the purposes of Schedule 9 is land to which a relevant planning permission relates. That is the reason the list may stand alone as the list refers to pre-existing recorded planning permissions in which the boundaries of the land subject to planning permission is defined and can be determined. It was at the next stage, where an applicant applies to the planning authority to determine the conditions to which the relevant planning permissions relate to the site are to be subject, that the applicants are required to give further specification about the site. This includes identification of the mineral site and any relevant planning permission relating to the site. It was at this next stage, if there was ambiguity about the boundaries of land to which planning permission applied, that the first respondents as planning authority were entitled to make a judgment based on the evidence and come to a view about the boundaries. Under reference to the affidavit of Andrew Brown (7/4 of process), senior counsel explained how the first respondents had approached the matter in the present case.
[12] Senior counsel submitted that if Schedule 9 was properly construed, it was plain that the legislation was not intended to give the planning authority power to "cut down" planning permission by listing only part of an area from a larger area to which the original planning permission applied. Although senior counsel conceded that the effect of paragraph 12 (4) is that in certain circumstances planning permission of a site not included in the first list shall cease to have effect, he emphasised that there were no words indicating that a planning permission might cease to have effect in relation to part of a site only. He also drew attention to paragraph 5 and pointed out that there were no provisions to re-advertise the amended first list and no provisions requiring the statutory listing or the paragraph 9 application for conditions to be intimated to land owners such as the petitioners. Although the listing is public, the main purpose of the legislative provisions is not to alter pre-existing planning permissions but to provide a mechanism particularly directed at the holders of planning permission, to ensure that they apply for appropriate conditions.
[13] Senior counsel stated that there were no averments in the petition critical of the methodology adopted by the first respondents in reaching their conclusion that planning permission extended to the red boundary area. The petitioners do not aver that as a matter of fact the pre existing planning permission before 1997 did not extend to the red boundary area. The foundation of the petition was limited and focused exclusively on the listing decision in 1997 and the effect thereof.
Submissions on behalf of the second respondents
[14] Senior counsel for the
second respondents explained at the start of his submissions that he did not
seek to rely on his plea to competency. He
submitted that the proper approach to resolve the case was to dismiss this
petition by sustaining the second respondents' plea to the relevancy. He submitted that no further procedure is
necessary.
[15] Senior counsel submitted that the issue to be determined at
first hearing was focused towards the end of paragraph 4 of the petition. The petitioners rely on the correspondence of
[16] Senior counsel submitted that issues of disputed fact do not arise in this case on the basis of the grounds averred in the petition. There is no dispute that the plan is lost. There are no averments challenging the approach adopted by the first respondents in reaching their decision that the land to which the planning permission was attached is the red boundary area. The petitioners' case is periled on the issue of whether the correspondence 6/1-3 of process is definitive of the boundary area and that therefore the boundary area is the green boundary area. If the petitioners are wrong in law about that, there is no other challenge averred in the petition. In particular it is not averred by the petitioners that the first respondents were not entitled to adopt the method they used in order to come to a decision about the extent of the planning permission. Senior counsel referred to Staffordshire Moorlands District Council v Cartwright and another 1992 J of Planning and Environment law 138, in support of the general proposition that where there was an ambiguity in the planning permission arising from the absence of plans, the planning authority was entitled to look at the evidence which existed to reach a decision. That is what the planning authority did in the present case.
[17] Senior counsel then briefly set out the context of Schedule 9. I did not understand his submissions to be different from those made by senior counsel for the first respondents. He supplemented this by reference to the Town and Country Planning Act 1997, section 36 which sets out the duties on the planning authority to keep a public register containing certain information. He submitted that this was the method set out in the legislation by which the public were enabled to find out the extent of planning permission in any particular case. The listing procedure under Schedule 9 did not refer to this and was independent of it. The purpose of the listing procedure was different from the provisions in section 36.
[18] Senior counsel emphasised that the planning authority in creating the first list is creating a list of areas of land for which relevant planning permission exists. He drew attention to the structure and purpose of the legislation. In particular in relation to Schedule 9, paragraph 6, he submitted that if the planning authority consider that part only of the land or interest is, or forms part of, any dormant site, they shall accede to the application so far as it relates to that part of the land or interest but shall otherwise refuse the application. He submitted that an appeal is only available if an application is refused in whole or in part. He submitted that properly interpreted, there was no refusal in the present case. In the present case the planning authority acceded to the application albeit making plain that they had no definitive plan. That matter therefor remains open. Senior counsel drew attention to the wording of Schedule 9, paragraph 12 and submitted that that paragraph does not deal with planning permission ceasing to have effect in relation to part of a site. The cessation of planning permission in terms of paragraph 12 relates to the relevant planning permission relating to the site.
Discussion
The legislative structure
[19] Schedule 9 makes
provision for the review of old mineral planning permissions. The Interpretation section provides:
"1. - (1) In this Schedule -...
'first list'....means the list preferred...pursuant to paragraph 3;
'mineral site' has the meaning given by sub-paragraph (2);....
'relevant planning permission' means any planning permission, other than an old mining permission or planning permission granted by a development order, granted after 30th June 1948 for minerals development;.....
(2) For the purposes of this Schedule, but subject to sub-paragraph (3), 'mineral site' means -......
(b) in any other case, the land to which a relevant planning permission relates.
(4) Any reference (however expressed) in this Schedule to an old mining permission or a relevant planning permission relating to a mineral site is a reference to the mineral site, or some part of it, being the land to which the permission relates."
[20] Schedule 9 paragraph 2 has effect for the purposes of determining which mineral sites are Phase 1 sites, Phase 2 sites or neither. Paragraph 3 (1) provides that "a planning authority shall..prepare a list of mineral sites in their area (the "first list"). Paragraph 3 (3) provides that in respect of each site included in the first list, the list shall indicate whether the site is an active Phase 1 site, an active Phase 2 site or a dormant site. Paragraph 4 makes provision in relation to the preparation of the second list. Paragraph 5 makes provision in relation to advertisement of the first and second lists.
[21] Schedule 9, Paragraph 6 makes provision for applications for inclusion in the first list of sites not included in that list as originally preferred and states:
"6. -(1) Any person who is the owner of any land, or is entitled to an interest in a mineral, may, if that land or interest is not a mineral site included in the first list and does not form part of any mineral site included in that list apply to the planning authority for that land or interest to be indicated in that list."
(2) An application under sub-paragraph (1) shall be made no later than the day upon which expires, the period of three months from the day when the first list was first advertised in accordance with paragraph 5.
(3) Where the planning authority considers that -
(a) the land or interest is, or forms part of, any dormant or active Phase I or II site, they shall accede to the application, or
(b) part only of the land or interest is, or forms part of, any dormant or active Phase I or II site, they shall accede to the application so far as it relates to that part of the land or interest,
but shall otherwise refuse the application.
(4) on acceding, whether in whole or in part, to an application made under sub paragraph (1), the planning authority shall amend the first list as follows.
(a) where they consider that the land or interest, or any part of the land or interest, is a dormant site or an active Phase I or II site, they shall add the mineral site consisting of the land or interest or, as the case may be, that part, to the first list and shall cause the list to indicate whether the site is an active Phase I site, an active Phase II site or dormant site;
(b) where they consider that the land or interest, or any part of the land or interest, forms part of any mineral site included in the first list, they shall amend the entry in the first list for that site accordingly....
(10) When a planning authority determine an application made under sub-paragraph (1), they shall notify the applicant in writing of their decision and, in a case where they have acceded to the application, whether in whole or in part, shall supply the applicant with details of any amendment to be made to the first or second list in accordance with sub-paragraph (4) or (8).
(11) Where a planning authority -
(a) refuse an application made under sub-paragraph (1), or
(b) accede to such an application only so far as it relates to part of the land or interest in respect of which it was made,
the applicant may by notice appeal to the Secretary of State.....
(13) An appeal under sub-paragraph (11) or (12) must be made by giving notice of appeal to the Secretary of State before the end of the period of six months beginning with - "
[22] Schedule 9 paragraph 9 provides that any person who is the owner of land, or who is entitled to an interest in a mineral, may, if that land or mineral is or... forms part of a dormant site ... apply to the planning authority to determine the conditions to which the relevant planning permissions relating to that site are to be subject." Such an applicant must specify in writing various matters including identifying the mineral site to which the application relates, identifying any relevant planning permission relating to the site and set out the conditions to which the applicant proposes the permissions should be subject. In terms of paragraph 9 (5) when such an application is received, the planning authority shall determine the conditions to which each relevant planning permission relating to the site is to be subject. In terms of paragraph 11, there is a right to appeal against the determination of conditions.
[23] Paragraph 12 deals with permissions ceasing to have effect. Paragraph 12 states:
"....
(3) Subject to sub-paragraph (4), no relevant planning permission, which relates to a dormant site shall have effect to authorise the carrying out of minerals development unless -
(a) an application has been made under paragraph 9 in respect of that site, and
(b) that permission has effect in accordance with paragraph 9 (5).
(4) A relevant planning permission which relates to a Phase I or II site not included in the first list shall cease to have effect, except in so far as it imposes any restoration or aftercare condition, on the day following the last date on which an application under sub-paragraph (1) of paragraph 6 may be made in respect of that site unless an application has been made under that sub-paragraph by that date in which event, unless the site is added to that list, such a permission shall cease to have effect when the following conditions are met
(a) the proceedings on that application, including any proceedings on or in consequence of the application under section 239 have been determined, and
(b) any time for appealing under paragraph 6(11) or (12), or applying or further applying under paragraph 6(1), (where there is a right to do so has expired)."
[24] In Schedule 9, paragraph 15, there are compensation provisions in specified circumstances. These circumstances do not include compensation for a listing ceasing to have effect in full or part.
Discussion
[25] This is a case in which the
statutory provisions and the factual background are complex. It is not disputed by the parties that
following correspondence 6/5 and 6/6 of process, the first respondents listed
Tullochgribban, Carrbridge, Baddingdock and Strathspey as a "dormant site" for
the purposes of the Environment Act 1995 section 96 (7/1 of process). I note that the said listing appears to have
taken place in July 1997 at a time when the statutory provisions had
essentially been re-enacted in respect of
[26] In order to reach a decision in this case, I consider it necessary to construe the language of Schedule 9 of the 1997 Act and consider in the context of the statutory structure, the meaning and effect of the documents in 6/5, 6/6 and 7/1 of process. I am prepared to accept the submission of senior counsel for the petitioner based on R v North Lincolnshire Council to the effect that the purpose of the legislation was to secure a definitive list of old mineral planning permissions continuing to subsist and to secure a new regime in respect of old mineral planning permissions conditions which adequately protect the environment during the operational period of the site with provision for appropriate aftercare and restoration in modern working practices.
I do not however consider that this case assists with the difficulty in the present case which arises because of the loss of the plan(s) which accompanied the old planning permission.
[27] It is plain from the legislation that if the site is not listed in the first list and if an owner of any land or entitled to an interest in a mineral does not make timeous application for inclusion in the list, that the pre-existing planning permission will be extinguished. In this case timeous application was made for inclusion in the list. This is not a case which falls within Schedule 9 paragraph 2(a). That was conceded correctly in my opinion, on behalf of the petitioners. The circumstances of this case fall within the type of circumstance set out in Schedule 9 paragraph 2(b). In my opinion that means that when a planning authority in accordance with paragraph 3 prepares a list of mineral sites within their area (the "first list") what they are preparing is a list of "the land to which a relevant planning permission relates". I consider that the intention of the legislation in relation to review of old mineral planning permissions in Schedule 9, is not to permit the planning authority to change the boundaries of land by reducing or increasing an area of land to which a relevant planning permission has been granted at an earlier date. The listing procedure envisages a listing of something which pre-exits i.e. the planning permission granted at an earlier date in respect of mineral sites. The form and content of the list is not otherwise specified in Schedule 9. In relation to Schedule 9 paragraph 2 (b) there is no obligation on the planning authority to have regard to any guidance issued by the Secretary of State. That is to be contrasted with the provisions in Schedule 9 paragraph 3. In terms of Schedule 9 paragraph 6, an application may be made for inclusion in the first list of sites if land or interest is not a mineral site included in the first list and does not form part of any mineral site so included. I accept that theoretically the planning authority for some reason might consider that they would be prepared to list part only of the land or interest as forming part of any dormant or active site. But in that event it is provided that the planning authority shall accede to the application so far as it relates to that part of the land or interest but shall otherwise refuse the application.
[28] In the present case the listing by the first respondents which
is to be found in 7/1 of process refers to the site name and this is a
reference, in terms of Schedule 9 paragraph 2(b) to the land to which
a relevant planning permission relates.
By checking the register of planning permissions, in terms of Section 36
of the 1997 Act a member of the public or any other interested party should be
able to discover that land defined. In
the present case the 1965 permission permitted "the working of minerals on land
at Tullochgorum, Carrbridge in accordance with the plan (s) submitted to the
council and docketed as relevant hereto".
By reference to that permission and the plan (s) it would be possible in
the normal case to identify the land by boundary or otherwise to which a
relevant planning permission relates.
Obviously the difficulty arises in this case because the plan (s)
has been missing since at least 1997. The logic of the submission on behalf of the
petitioners is that even if the missing plan (s) was now found that would
not affect the outcome of the case in relation to the boundary of land to which
a relevant planning permission relates.
The petitioners' submissions, which I summarise in paragraph 3, are
to the effect that following the correspondence of 6/5 and 6/6 of process the
correspondence, the first respondents as planning authority in effect
restricted the land to which a relevant planning permission relates to the green
boundary area when they made the listing in 7/1 of process. I do not consider that the submissions on
behalf of the petitioners are well founded.
I am of the opinion that the correspondence must be construed against
the background of the statutory scheme.
The application was an application to register Tullochgribban Quarry
(known as Tullochgorum in respect of the planning permission) in terms of the planning
permission 1964/798 granted on 12 February 1965. The original plan(s) attached to said
planning permission was not enclosed and was not available to the first
respondents. Whatever the first
respondents thought they were listing at the time, they purported to list the
site as Tullochgribban, Carrbridge in terms of the planning permission
[29] I accept that an issue of fact arises as to the extent of the boundaries of land to which the 1965 planning permission attached, in terms of planning reference ICC/1964/798 because of the absence of the original definitive plan(s). As I understand the grounds of the petition and the submissions on behalf of the petitioners, the petitioners do not accept the first respondents' approach to the determination of the boundaries. There are no averments in the petition and no submissions were made to found grounds of judicial review in relation to this aspect of the case. If such grounds had been put forward, I consider it would probably have been necessary to order some form of proof.
[30] I appoint the case to the By Order roll to permit parties to address me about disposal of the pleas in the light of my opinion and to address me in relation to expenses.